Tohid-3

Tohid-3
This project involved the design and execution of wall stabilization operations using nailing, anchoring, truss shoring (retaining structures), and corner bracing methods. Given the presence of high-rise, sensitive buildings in the immediate vicinity and the encounter of groundwater at a depth of 16 meters, the stabilization process was executed with a specialized, risk-based approach. The entire operation was completed in 90 days, in full compliance with all technical and safety standards.
Location
Shahrak-e Gharb
Stabilization Method
Nailing, Anchoring, Truss Retaining Structure, and Corner Bracing
Activity
Excavation and Wall Stabilization
Client
Mr. Engineer Fazeli
Excavation Depth
16.5 meters
Start Date
01 December 2024
Execution Time
90 Days